New Pedestrian Access Gate & footway

Project Overview

Civils and Environmental Ltd were appointed to undertake the installation of a secure pedestrian access gate and integrated electronic access control system.

The project combined civil groundworks, reinforced concrete construction, steel gate installation, and advanced access control integration near a live substation environment. Due to proximity to electrical infrastructure, all excavation works were carefully controlled and hand-dug where required.

This scheme was designed to improve perimeter security, safe pedestrian access, and controlled entry management within an operational industrial site.

Site Assessment & Pre-Construction Planning

Prior to mobilisation, a detailed site assessment and risk review were undertaken. Key site considerations included:

  • Vehicle and pedestrian interface risks

  • Proximity to electrical substation infrastructure

  • Restricted digging zones

  • Requirement for CAT scanning during works

  • Controlled site sign-in and induction procedures

Given the location near live electrical equipment, all excavation works were planned as hand-dig operations to mitigate risk of striking buried services.

The team developed a method statement and sequencing programme to ensure works could be completed safely and efficiently with minimal operational disruption.

Phase 1: Civil Engineering & Groundworks

Concrete Pad & Sub-Base Construction

To accommodate the new gate structure, Civils and Environmental constructed:

  • A 3.5m x 1.5m reinforced concrete pad (150mm thick)

  • Installed over 200mm of MOT Type 1 compacted sub-base

  • Designed to provide long-term load-bearing stability

  • Finished to level tolerance suitable for secure gate operation

The reinforced pad ensures resistance to cracking, settlement, and vibration from nearby vehicle movements.

Apollo 868 Gate Installation

A 3m x 1.2m Apollo 868 single-leaf dig-in mesh gate was installed, providing:

  • Secure steel perimeter access

  • Dig-in mesh design to prevent ground-level breach

  • Durable galvanised finish for corrosion resistance

Posts were securely concreted into position, ensuring structural integrity and compliance with industrial perimeter security standards.

Access Steps Installation

A 1.2-metre-wide concrete step arrangement was constructed to allow safe pedestrian access up to the newly formed pad, ensuring:

✔ Safe level transition
✔ Improved access usability
✔ Compliance with safe access principles

Steel Trunking Installation

To facilitate cable routing, 7 metres of Salamandre 50mm x 50mm galvanised steel trunking were installed along the existing fence line. This trunking connected into underground ducting leading to the site power supply, ensuring:

  • Protected cable containment

  • Weather resistance

  • Mechanical protection in industrial conditions

Phase 2: Electronic Access Control Installation

The project included full integration of an access control system to manage pedestrian entry.

System Design Proposal (SDP)

The system comprised:

  • Salto access reader installed externally on the new pedestrian gate

  • External-grade Request to Exit (RTE) button

  • Green external Break Glass Unit (BGU)

  • S500 external-grade enclosed gate maglock with brackets

This configuration delivers controlled access from both secure and non-secure sides while complying with safety and emergency egress requirements.

Access Control Installation Methodology

Control Panels

  • Mounted on structurally sound internal surfaces

  • Installed at secure, serviceable height

  • Cabling routed via trunking or concealed containment

  • Mains power connected in approved terminations

Break Glass Unit (BGU) & Request to Exit (RTE)

  • Installed at approximately 1.2m height

  • Positioned to comply as closely as possible with DDA accessibility principles

  • Flush cabling through walls where feasible

Salto Reader

  • Installed at approx. 1.2m height for accessibility

  • Cabling concealed where possible

  • Secure termination within junctions on the protected side

Maglock Installation

  • Installed using L or I brackets as required

  • Secure mechanical fixing to structural frame

  • Armature plate mounted to gate leaf

  • Cabling concealed internally or protected in conduit

This structured installation approach ensures system durability, operational reliability, and compliance with controlled-access best practice.

Operational & Safety Management

Working Hours & Programming

Works were planned to allow flexibility between 06:00 – 20:00 to minimise risk and operational disruption. Where possible, higher-risk activities were scheduled outside normal working hours.

A post-installation “bedding-in period” was allowed for final system adjustments and user calibration.

PPE & Safety Controls

Engineers were equipped with:

  • Safety boots (midsole protection)

  • Hard hats

  • Safety glasses

  • Rigger gloves

  • Respiratory dust masks

Strict adherence to site safety and controlled excavation protocols was maintained throughout.

Outcome & Client Benefits

✔ Secure pedestrian access point installed
✔ Reinforced concrete pad providing long-term structural integrity
✔ Integrated Salto-controlled electronic access system
✔ DDA-conscious hardware positioning
✔ Secure maglock and emergency release functionality
✔ Safe completion in proximity to substation

More Projects

Boston, MA

New Pedestrian Access Gate & footway

Boston, MA

New Pedestrian Access Gate & footway

Boston, MA

New Pedestrian Access Gate & footway

Boston, MA

New Pedestrian Access Gate & footway

Boston, MA

Warehouse Drain repairs

Boston, MA

Warehouse Drain repairs

Boston, MA

Warehouse Drain repairs

Boston, MA

Warehouse Drain repairs

We are looking forward to working with you

We are looking forward to working with you

Let’s Discuss

Let’s Discuss

Schedule a Free Consultation

© 2023 All Right Reserved by Civils and Environmental Ltd

© 2023 All Right Reserved by Civils and Environmental Ltd

© 2023 All Right Reserved by Civils and Environmental Ltd

© 2023 All Right Reserved by Civils and Environmental Ltd