Entrance Modifications
Island Construction & Duct Installation
Project Overview
Civils and Environmental Ltd were appointed to deliver the construction of a new security island and underground duct installation.
The works were programmed across two consecutive weekends to minimise disruption to the operational car park and maintain barrier functionality during the working week.
The project involved:
CAT scanning and controlled hand excavation
Installation of new ducting to serve a relocated card reader
Construction of a reinforced concrete island base
Kerbing installation and block paving reinstatement
Thermoplastic road markings and final finishing works
The scheme required careful sequencing to ensure the electrician could reconnect the access reader by Sunday lunchtime, reducing downtime to site operations.
Phase 1: Pre-Start & Enabling Works (Friday)
Prior to ground disturbance, the team undertook:
CAT Scan & Service Identification
Cable avoidance tool (CAT) scanning of the work area
Marking out of underground services
Identification of safe hand-dig zones (first 150mm excavated by hand)
This ensured safe excavation in a live commercial car park environment.
Deliveries were coordinated and received in preparation for weekend mobilisation.
Phase 2: Weekend 1 – Duct Installation & Island Base Construction
Saturday Works
Traffic & Site Control
Barriered off the front of the car park
Established safe segregation zones
Installed cones and signage
Duct Installation
Cutting of existing surfacing using a Stihl saw
Breaking out with hand breakers
Controlled hand excavation
Installation of new ducting from existing reader position to new island location
This provides protected infrastructure for the relocated security access reader system.
Blockwork Removal
Existing block paving was removed (assumed sand bed installation).
Note: If blockwork had been found embedded in concrete, additional labour and materials would have been required (identified within exclusions).
Concrete Pad Installation
Excavation to required formation
Preparation of sub-base
Installation of C40 readymix concrete for enhanced strength and durability
Formation of structural base for new security island
Kerbing Installation
New kerbs installed, prioritising the reader area
Alignment completed to allow infrastructure positioning
Sunday Works (Weekend 1)
Continuation and completion of ducting and concrete works
Target completion of concrete pad prior to Sunday lunchtime
Coordination with electrician for reconnection of access reader
Upon completion:
Barriers removed
Cones and barrier tape left in place
Work area safely cordoned while maintaining operational vehicle barrier access during the week
This phased approach ensured minimal operational downtime for the client.
Phase 3: Weekend 2 – Final Reinstatement & Markings
Saturday (Completion of Island & Reinstatement)
Completion of security island structure
Reinstatement of surrounding block paving
Reinstatement of adjacent cycleway
Site cleaned and prepared for surface markings
Surface preparation is critical prior to thermoplastic application to ensure adhesion and long-term durability.
Sunday (Line Marking & Finishing Works)
Thermoplastic Road Markings
Surface primed where required
Gas torch application of thermoplastic banding
Installation of hatching and/or symbols
Thermoplastic markings were selected for:
✔ High visibility
✔ Long lifespan
✔ Abrasion resistance
✔ Suitability for commercial car parks
Installation of New Post
Installation into designated soil area
Secured and aligned to specification
Engineering & Material Specification
Hand-dig excavation (first 150mm)
Stihl saw surface cutting
Hand breaker removal
C40 readymix structural concrete
New kerbing installation
Underground ducting installation
Block paving reinstatement
Thermoplastic line marking system
Exclusions Clarified
The following items were excluded from the agreed scope:
Additional labour/materials if block paving was found embedded in concrete
Removal or amendment of existing barriers
Supply of specified post
These exclusions ensure transparent scope control and cost clarity.
Operational Benefits
✔ Safe underground service installation
✔ New structural security island base
✔ Minimal disruption through phased weekend working
✔ Durable C40 concrete installation
✔ Professional thermoplastic road markings
✔ Coordinated works enabling prompt reconnection of security systems